Banksia Station Upgrade
Client: Downer
Duration: 10 Months
Date of Completion: December 2021
​
Elecdata completed electrical and communications upgrades to the station, including lift install as part of the Transport for NSW Transport Accessibility Upgrade Rollout.
​
Scope of works include:
• New isolation transformer including dual supplies and new mains to installation main switchboard
• Electrical and lighting throughout the station
• Mains, submains, and power to lifts
​• Communications and network cabling
​• CCTV installation
​• platform information screens, cabling, and installation
​• Public address system
​• Ticketing systems installation
​