Berala Station Upgrade
Client: Arenco
Duration: 8 Months
Date of Completion: August 2017
Value: $651k
​
Electrical & communications upgrade to station as part of Transport for NSW Transport Accessibility Upgrade Rollout.
​
Scope of works include:
• Supply, installation and commissioning of pad mount Isolation Transformer
• Electrical and lighting throughout the station
• Mains, submains, and power to lifts
​• Communications and network cabling
​• CCTV Install
• Station platform information screens cabling and installation
​• Public address system
​• Ticketing systems installation
​