Petersham Station Combined Services Route

Client: Arenco

Duration: 3 Days
Date of Completion: August 2020

Combined CSR route installation over a possession weekend.

Works involved saw cutting of bitumen platform, excavation of material, installation of pits and conduit, installation of sand, back filling and compaction, cleaning and make good to platform.

Scope of works include:

•  Saw cutting 200m of trench and pit profile

•  Installation of 900m of conduit

•  Installation of pits

​•  Additional precautions due to station being heritage listed​

​•  Custom designed conduit layout  & spacers to suit specific site requirements